Second World War Gallery, Imperial War Museum
The Second World War Gallery (Exhibition Designer: Ralph Applelbaum Associates) provides IWM London for the very first time with a complete exhibition exploring the course of the Second World War from its beginnings to its conclusion, detailed in its full global context and importantly, in parallel with the historical course of the holocaust, which at one point is linked with this exhibition through a double height space connecting the two galleries around a single artefact linked to both narratives. The look and feel of this gallery connects directly to the First World War gallery on the level below, but there is a much greater emphasis within the new exhibition towards connecting artefacts to the personal stories of individuals experiencing all aspects of a global conflict that was of unprecedented scale in all of human history.
Phases 2A and 2B of the Foster Masterplan for IWML were combined in 2016 to create a single project to create two new galleries telling the story of Britain and the Commonwealth during the Second World War and that of the Holocaust. These galleries, which opened in November 2021, have built upon the high standards for narrative based museums set by IWM in its First World War Galleries.
The overall project consisted of the design, construction and exhibition fit out of these new galleries within the Grade II listed building, together with a refresh of the Second World War Atrium Terrace displays. Alongside the new galleries, the project also included the creation of new learning and events spaces on Levels 1 and 2.
DJA were appointed as Lead Consultants for the gallery basebuild design team under a multi-disciplinary arrangement where we had put together a team of sub-consultants including structural engineers David Rafferty of Mason Navarro Pledge and Steensen Varming as mechanical, electrical and lighting engineers.
Leading this multidisciplinary team, we collaborated to provide a fully detailed spatial, structural and services design for the base build infrastructure works in accordance with the exhibitions design and fit out requirements. This involves working around existing and new structural interventions, reusing existing plant rooms and risers where possible in order to distribute services and enable the vision for the galleries to take shape.
The project involved working with two separate exhibition design teams, to develop two distinct but interlinked galleries.
Our team sought to fully understand the creative vision and narrative of each exhibition design to develop meaningful visitor flow, and constructive solutions for the built fabric and systems serving the galleries.
To create these spaces, we needed to open up the existing fabric to create more than 2,500m2 of internal floor area over two floors, knitting together existing structures of different ages and constructions and inserting major structural interventions to create additional floor space. Former back of house storage areas, teaching and schools spaces, conference rooms, the central cinema and two self-contained galleries were all subsumed into the overall footprint. Many of which were on different part-level heights, necessitating consideration of ramps and accessibility within the wider circulation.
Crucially, we managed to create workable spaces without needing to carry out any work to the existing foundations, although some works to remove existing internal loadbearing walls were very complex.
The two floors of galleries under construction were sandwiched between the First World War exhibition on Level 0 and the previous Holocaust Galleries on Level 3. Both of these Galleries were fully open to the public throughout the works, including a phase of demolitions lasting around seven months, except for when the Museum was forced to close because of the pandemic.
A three year design process involved numerous meetings with many different stakeholders to ensure coordination and communication between the various teams that were required to create the new exhibitions including: the Museum’s internal team of project managers, curators, collections and conservation staff, and academic review panels, film and media producers and mountmakers; Project Managers, Cost consultants, AV systems designers, Access Consultants, Fire Engineers, and the appointed Approved Inspectors; the exhibitions design teams with their sub-consultant lighting designers, graphics consultants, interactives designers, soundscape designers, film and media producers.
The result are two experientially contrasting spaces, with inextricably linked themes. IWM Lambeth is the first museum in the world to house both displays under the same roof.
In 2022, the galleries won Museums + Heritage Permanent Exhibition of the Year Award.
Filed to: Heritage, Arts and Museums